Which one of the following activities are carried out during the “Where do we want to be?” step of the continual service improvement (CSI) approach?

QuestionsCategory: ITILFWhich one of the following activities are carried out during the “Where do we want to be?” step of the continual service improvement (CSI) approach?
Admin Staff asked 10 months ago
Which one of the following activities are carried out during the "Where do we want to be?" step of the continual service improvement (CSI) approach?

A. Implementing service and process improvements

B. Reviewing measurements and metrics

C. Creating a baseline

D. De ning measurable targets










Correct Answer: D

This question is in ITIL Foundation exam