Which of the following Availability Management activities are considered to be proactive as opposed to reactive? (1) Risk assessment (2) Testing of resilience mechanisms (3) Monitoring of component availability

QuestionsCategory: ITILFWhich of the following Availability Management activities are considered to be proactive as opposed to reactive? (1) Risk assessment (2) Testing of resilience mechanisms (3) Monitoring of component availability
Admin Staff asked 1 year ago
Which of the following Availability Management activities are considered to be proactive as opposed to reactive?
(1) Risk assessment
(2) Testing of resilience mechanisms
(3) Monitoring of component availability

A. All of the above

B. 1 and 2 only

C. 1 and 3 only

D. 2 and 3 only










Correct Answer: B

This question is in ITIL Foundation exam
For getting ITIL Foundation Certificate



Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.