A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met. What should the project manager do? A. Discuss and agree with the customer to implement the missing requirement B. Refer to the requirements traceability matrix and analyze the requirement C. Consult the scope management plan with the customer to understand the gap D. Analyze the benefits management plan and implement the needed change Correct Answer: B This question is in PMP exam For getting PMP Certificate