Eight highly quali ed experts have been assembled to work for a 6-month period on a specific aspect of an organization’s product development process. How should the project manager support this team to succeed?

QuestionsCategory: PMPEight highly quali ed experts have been assembled to work for a 6-month period on a specific aspect of an organization’s product development process. How should the project manager support this team to succeed?
Admin Staff asked 1 year ago
Eight highly quali ed experts have been assembled to work for a 6-month period on a specific aspect of an organization's product development process.
How should the project manager support this team to succeed?

A. define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.

B. Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.

C. Work with the team members to define the overall objective and support them to engage around the goal.

D. Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.