A customer has provided excellent feedback on the project. However, a key project resource is leaving the company. Which measure should mitigate the impact of this key resource’s departure?

QuestionsCategory: PMPA customer has provided excellent feedback on the project. However, a key project resource is leaving the company. Which measure should mitigate the impact of this key resource’s departure?
Admin Staff asked 11 months ago
A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource's departure?

A. Establish a proactive knowledge-sharing plan

B. Offer a new contract to the resource who is leaving

C. Develop a contingency budget to replace the key resource

D. Update the risk register and inform the customer










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.