A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

QuestionsCategory: PMPA business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?
Admin Staff asked 1 year ago
A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach.
What strategy should the project manager use to persuade the stakeholder to use an agile approach?

A. Agree on a predictive approach, but apply agile concepts under the project management umbrella.

B. Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

C. Document the request and escalate to upper management to consider a modification of the project charter.

D. Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.