A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach? A. Agree on a predictive approach, but apply agile concepts under the project management umbrella. B. Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time. C. Document the request and escalate to upper management to consider a modification of the project charter. D. Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery. Correct Answer: D This question is in PMP exam For getting PMP Certificate