The project manager is reviewing a project's progress and notices that one of the risks has become an issue.
What should the project manager do to address the situation?

A. Initiate a change request to obtain additional funds from the management reserve

B. Meet with the project team and customer to brainstorm about potential solutions

C. Schedule a high-priority meeting with the project stakeholders to discuss the issue

D. Collaborate with the relevant stakeholders on implementing the risk response plan










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.