A project manager is part of a balanced matrix project organization. The project manager will receive all work performance updates directly from the new sourcing department head who has no time to spare to give the project manager the information. What should the project manager do? A. Discuss the situation with the company project sponsor for advice B. Request information directly from the sourcing department team members C. Work out a resolution in consultation with the sourcing department head D. Present the situation to the manager of the sourcing department head Correct Answer: C This question is in PMP exam For getting PMP Certificate