A project manager recently nished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor. What should the project manager do to resolve this con ict? A. Ensure the new supervisor takes the lead when being challenged B. Give the project team time to work through the issues with the new supervisor C. Immediately remove the resource from the project team D. Communicate with the resource on the roles and responsibilities of this project D Correct Answer: D This question is in PMP exam For getting PMP Certificate