Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before. How should the agile project leader resolve this situation?

QuestionsCategory: PMPTwo team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before. How should the agile project leader resolve this situation?
Admin Staff asked 1 year ago
Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
How should the agile project leader resolve this situation?

A. Update the project budget with the released team members.

B. Update the restriction log with the new team capacity.

C. Explain the new project requirements to the team.

D. Explain the new team velocity to the customer.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.