During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to be involved in the regular project communications and reporting cycles. What should the project manager do? A. Ask the project team members to include the manager in all of their communications regarding this project. B. Inform the manager that only stakeholders identified in the communications management plan should be involved. C. Perform a stakeholder analysis and update the communications management plan to re ect the new situation. D. Suggest the manager contact the steering committee and project management office (PMO) to be included. Correct Answer: C This question is in PMP exam For getting PMP Certificate