A team has had issues with behavior on an ongoing project, which is causing con icts. As a result, the team is losing momentum and falling behind in its sprints. How should the project manager handle this situation? A. Engage a counselor to reconcile the situation between the team members affected. B. Control backlog assignments and reduce direct communications between team members. C. Revisit the ground rules and team communication protocols, and discuss what is happening. D. Require team members experiencing the con icts to take a day off from work. Correct Answer: C This question is in PMP exam For getting PMP Certificate