A new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting. What should the project manager do?

QuestionsCategory: PMPA new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting. What should the project manager do?
Admin Staff asked 11 months ago
A new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting.
What should the project manager do?

A. Obtain related training for the new team member.

B. Determine the appropriate level of decision-making authority and empower the engineer.

C. Make all of the decisions for the engineer in order to keep the work flow on track.

D. Replace the resource with an experienced engineer.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.