A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization and asks the project manager to pay attention to changes that can affect the project. Which action should the project manager take to identify changes that may affect the product?

QuestionsCategory: PMPA project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization and asks the project manager to pay attention to changes that can affect the project. Which action should the project manager take to identify changes that may affect the product?
Admin Staff asked 1 year ago
A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization and asks the project manager to pay attention to changes that can affect the project. Which action should the project manager take to identify changes that may affect the product?

A. Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

B. Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

C. Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

D. Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.