A project manager is performing the role of scrum master for a team of developers. There is a con ict among the developers, generated by differences in how a feature can be delivered. The project manager organized a few spikes to resolve this con ict. What should the project manager do next? A. Organize a multivoting event to achieve consensus of the whole team. B. Allow the team to decide on their own which option should be implemented. C. Organize more spike events until consensus of the team is reached. D. Ask the project sponsor to decide which option should be implemented. Correct Answer: B This question is in PMP exam For getting PMP Certificate