A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager’s emails are very harsh. What should the project manager do to solve this situation?

QuestionsCategory: PMPA project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager’s emails are very harsh. What should the project manager do to solve this situation?
Admin Staff asked 1 year ago
A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.
What should the project manager do to solve this situation?

A. Determine the level of in uence of the stakeholders who are complaining.

B. Change the communication mode from emails to meetings to reduce stakeholders complaints.

C. Adjust the communications management plan to gain stakeholder trust.

D. Explain to the sponsor that the communication model being used is from company headquarters.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.