A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it. Which approach should the project manager use as a servant leader?

QuestionsCategory: PMPA project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it. Which approach should the project manager use as a servant leader?
Admin Staff asked 1 year ago
A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.
Which approach should the project manager use as a servant leader?

A. Escalate the issue with upper management to find a novel solution for this situation.

B. Contact the project sponsor to get those stakeholders removed from the project.

C. Allocate resources to provide training about the new technology to the stakeholders.

D. Ask stakeholders to find and self-fund education about this new technology.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.