A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects. How can the project manager strategize the use of a hybrid approach to the organization? A. Submit a notification to the project team confirming they will be using a hybrid approach on the project. B. Send a letter to the project management office (PMO) requesting to use a hybrid approach. C. Create a project change request to execute the project using a hybrid approach. D. Present the benefits of a hybrid approach to key stakeholders to get their support. Correct Answer: D This question is in PMP exam For getting PMP Certificate