A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects. How can the project manager strategize the use of a hybrid approach to the organization?

QuestionsCategory: PMPA company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects. How can the project manager strategize the use of a hybrid approach to the organization?
Admin Staff asked 1 year ago
A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects. How can the project manager strategize the use of a hybrid approach to the organization?

A. Submit a notification to the project team confirming they will be using a hybrid approach on the project.

B. Send a letter to the project management office (PMO) requesting to use a hybrid approach.

C. Create a project change request to execute the project using a hybrid approach.

D. Present the benefits of a hybrid approach to key stakeholders to get their support.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.