The project manager has learned that the project sponsor is unhappy with the development of the project requirements. In order to realign the project with the sponsor's expectations, what should the project manager do? A. Review the project goal diagram with the team B. Perform a stakeholder evaluation C. confirm which templates the team should be using D. Review the risk management plan Correct Answer: B This question is in PMP exam For getting PMP Certificate