A company has decided to implement a new archiving system. A data breach occurred during the implementation of the project. What should the project manager do first? A. Implement the planned risk response to handle the issue B. Review possible alternative documentation methods with team C. Update the risk register with the risk and proposed impact D. Ask the team to fix the system to resolve the issue Correct Answer: A This question is in PMP exam For getting PMP Certificate