A client mentioned that in the past 2 months, they have not been invoiced for completed work. The client has communicated that they will release the funds for other activities it the invoices are not sent. What should the project manager do next?

QuestionsCategory: PMPA client mentioned that in the past 2 months, they have not been invoiced for completed work. The client has communicated that they will release the funds for other activities it the invoices are not sent. What should the project manager do next?
Admin Staff asked 1 year ago
A client mentioned that in the past 2 months, they have not been invoiced for completed work. The client has communicated that they will release the funds for other activities it the invoices are not sent.
What should the project manager do next?

A. Work with the client and agree on a schedule to provide them with the invoices

B. Reach out to the billing team and instruct them to issue the invoices immediately

C. Review the previous billing information and prepare a corrective action plan

D. Communicate and inform the client to go ahead and release the funds










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.