After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month. What should the project manager do? A. Change the kick-off meeting to a virtual meeting so all can attend at the same time. B. Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project. C. Reschedule the kick-off meeting for the following month so all can attend on-site. D. Make arrangements for the stakeholder to join the kick-off meeting virtually. Correct Answer: D This question is in PMP exam For getting PMP Certificate