In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and

QuestionsCategory: PMPIn a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and
Admin Staff asked 1 year ago
In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and

A. Country B discovers that one of the legal requirements was not addressed.
What should the project manager have done to avoid this situation?

B. Managed risk mitigation strategies specific to each country.

C. Asked procurement to assign resources located in each country.

D. Selected countries that had similar regulatory requirements.

E. identified the regulatory differences among the countries.








Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.