A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users. What should the project manager do next? A. Discuss the issue with the team member in a one-on-one meeting. B. Escalate the performance issue to the team member's functional manager. C. Ask the team member to justify the delay during a team meeting. D. Review the human resources (HR) policies for relevant corrective actions. Correct Answer: A This question is in PMP exam For getting PMP Certificate