In a project progress review meeting, the end user raises concern about the quality of the construction of the project. What should the project manager do next?

QuestionsCategory: PMPIn a project progress review meeting, the end user raises concern about the quality of the construction of the project. What should the project manager do next?
Admin Staff asked 1 year ago
In a project progress review meeting, the end user raises concern about the quality of the construction of the project. What should the project manager do next?

A. Request a special technical meeting.

B. Refer to the requirements document.

C. Review the risk management plan.

D. Review all implementation checklists.










Correct Answer: B

This question is in PMP exam