In a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule. What should the project manager do?

QuestionsCategory: PMPIn a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule. What should the project manager do?
Admin Staff asked 1 year ago
In a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule.
What should the project manager do?

A. Keep the project sponsor informed about the delay.

B. Reassign the task to another member of the team.

C. Support the team member by providing one more resource to complete the task immediately.

D. Ask the team member if there is an impediment, and help to remove the blockers.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.