The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete. The project manager reviews the work breakdown structure (WBS) and confirms that the component is included. What does the project manager need to do first?

QuestionsCategory: PMPThe customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete. The project manager reviews the work breakdown structure (WBS) and confirms that the component is included. What does the project manager need to do first?
Admin Staff asked 1 year ago
The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete.
The project manager reviews the work breakdown structure (WBS) and confirms that the component is included.
What does the project manager need to do first?

A. Ask the project team to conduct a quality audit of the printing module components.

B. Meet with the project team to understand the issue and define actions.

C. Escalate this issue to the project sponsor immediately.

D. Raise a change request to immediately implement the printing module component.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.