A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client's needs. Which factor should the project manager have considered when developing the product? A. Responsibility matrix B. Stakeholder's location C. Availability of resources D. Stakeholder's needs Correct Answer: D This question is in PMP exam For getting PMP Certificate