In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time. What should the project manager do first? A. Assess the schedule and update the risk register. B. Report the delay to all other subcontractors. C. Change the milestones and sequence of work. D. Escalate to senior management and the stakeholders. Correct Answer: A This question is in PMP exam For getting PMP Certificate