During the execution phase of a project, one of the customer’s stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)

QuestionsCategory: PMPDuring the execution phase of a project, one of the customer’s stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)
Admin Staff asked 1 year ago
During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)

A. Update the relevant project documents with this obstacle.

B. Highlight the impacts of the changes during the next project meeting.

C. Adjust the project management plan to include the changes in scope.

D. Continue the execution as planned and defer the changes to a future phase.

E. Schedule a meeting with the customer to align the approach.








Correct Answer: ABE

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.