0 A project team was asked to resume development activities on a project that was suspended for a few months due to the fast-changing environment and conditions. What should the project lead do? A. Review the items remaining in the backlog with the project team B. Ask the project team to approve all of the remaining backlog items C. Ask the program manager to approve the backlog with the client D. Review the items remaining in the backlog with the project sponsor Correct Answer: A This question is in PMP exam For getting PMP Certificate