A senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and girves instructions to the other project managers directly. What should the senior project manager do?

QuestionsCategory: PMPA senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and girves instructions to the other project managers directly. What should the senior project manager do?
Admin Staff asked 1 year ago
A senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and girves instructions to the other project managers directly.
What should the senior project manager do?

A. Tell the project managers to document the stakeholder's instructions.

B. Evaluate the stakeholder analysis to identify the stakeholder's in uence.

C. Review the benefits realization plan with the sponsor and the stakeholder.

D. Escalate to the project sponsors and the manager of this stakeholder.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.