You are the project manager of HWD project. It requires installation of some electrical machines. You and the project team decided to hire an electrician as electrical work can be too dangerous to perform. What type of risk response are you following? A. Avoidance B. Transference C. Mitigation D. Acceptance Suggested Answer: B As the risk is transferred to the third party (electrician), hence this type of risk response is transference. Incorrect Answers: A: Risk avoidance means to evade risk altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event. Risk avoidance is applied when the level of risk, even after the applying controls, would be greater than the risk tolerance level of the enterprise. C: Risk mitigation attempts to reduce the probability of a risk event and its impacts to an acceptable level. Risk mitigation can utilize various forms of control carefully integrated together. D: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.
Please login or Register to submit your answer