You are the project manager in your enterprise. You have identified occurrence of risk event in your enterprise. You have pre-planned risk responses. You have monitored the risks that had occurred. What is the immediate step after this monitoring process that has to be followed in response to risk events? A. Initiate incident response B. Update the risk register C. Eliminate the risk completely D. Communicate lessons learned from risk events  Suggested Answer: A When the risk events occur then following tasks have to done to react to it: ✑ Maintain incident response plans ✑ Monitor risk ✑ Initiate incident response ✑ Communicate lessons learned from risk events This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.