Which of the following tasks should be completed prior to creating a disaster recovery plan (DRP)? A. Procuring a recovery site B. Conducting a business impact analysis (BIA) C. Assigning sensitivity levels to data D. Identifying the recovery response team Suggested Answer: B This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.