John is the project manager for a large project in his organization. A new change request has been proposed that will affect several areas of the project. One area of the project change impact is on work that a vendor has already completed. The vendor is refusing to make the changes as they've already completed the project work they were contracted to do. What can John do in this instance? A. Withhold the vendor's payments until the issue is resolved. B. refer to the contract agreement for direction. C. Refer the vendor to the Service Level Agreement (SLA) and insist that they make the changes. D. Review the Request for proposal (RFP) for guidance. Â Suggested Answer: B This question is in 712-50 EC-Council Certified CISO (CCISO) Exam For getting EC-Council Certified CISO (CCISO) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by EC-Council. Trademarks, certification & product names are used for reference only and belong to EC-Council. The website does not contain actual questions and answers from EC-Council's Certification Exam.
Please login or Register to submit your answer