2 In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

QuestionsCategory: PMP2 In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
Admin Staff asked 1 year ago
2  
In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

A. Empower the team members to do their work.

B. Work with the team to develop a risk response plan.

C. Send an email to human resources (HR) about this situation.

D. Inform the project sponsor about this situation.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.