A business transformation project has a four-phase delivery plan. The project team has successfully delivered one phase of the project. To further enhance team performance and empower team members, which two actions should the project manager take? (Choose two.)

QuestionsCategory: PMPA business transformation project has a four-phase delivery plan. The project team has successfully delivered one phase of the project. To further enhance team performance and empower team members, which two actions should the project manager take? (Choose two.)
Admin Staff asked 1 year ago
A business transformation project has a four-phase delivery plan. The project team has successfully delivered one phase of the project. To further enhance team performance and empower team members, which two actions should the project manager take? (Choose two.)

A. Encourage team members to cross-check decisions with the project manager.

B. Vet all of the decisions before execution.

C. Allow team members to make limited decisions.

D. Organize and assign team members to tasks where they have strengths.

E. Support team members to make decisions in their areas of strength.








Correct Answer: DE

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.