A client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client’s organization on the email. What should the project manager do?

QuestionsCategory: PMPA client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client’s organization on the email. What should the project manager do?
Admin Staff asked 1 year ago
A client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client's organization on the email.
What should the project manager do?

A. Contact the other manager and ask them to delete the email.

B. Inform the client and their supervisor about the mistake.

C. Wait for the client's feedback regarding the report.

D. Resend the email to the client, excluding the other manager.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.