QuestionsCategory: PMPA company has a lot of experience with predictive projects. The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project. After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project. What should the project manager do?
Admin Staff asked 1 year ago
A company has a lot of experience with predictive projects. The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project. After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.
What should the project manager do?

A. Determine the data to be monitored during the project as well as the expected performance and targets.

B. Update the communications management plan to consider performance review meetings with the project stakeholders.

C. Prepare and submit a status report to the steering committee to update performance monitoring.

D. Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.