A company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price. What should have been done differently to avoid this scenario?

QuestionsCategory: PMPA company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price. What should have been done differently to avoid this scenario?
Admin Staff asked 1 year ago
A company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price.
What should have been done differently to avoid this scenario?

A. A minimum viable product (MVP) should have been released to get feedback from the market.

B. More backlog re nement meetings should have been scheduled.

C. The Kanban method should have been utilized to optimize the work in progress (WIP).

D. An iterative life cycle approach should have been adopted.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.