A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects. Which tool should the project manager use for this purpose? A. Forecast estimation B. Earned value (EV) C. Cumulative flow diagram D. Burndown chart Correct Answer: B This question is in PMP exam For getting PMP Certificate