A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements. How should the project manager plan the delivery of the project?

QuestionsCategory: PMPA company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements. How should the project manager plan the delivery of the project?
Admin Staff asked 1 year ago
A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?

A. Ignore the unclear requirements and focus on the delivery plan of the project.

B. Wait for the requirements to be more clear before any further action is taken on the project.

C. Break down the requirements and prioritize the requirements into iterative work packages.

D. Escalate the issue of unclear requirements to the management team and wait for final authorization.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.