A control for mitigating risk in a key business area cannot be implemented immediately. Which of the following is the risk practitioner's BEST course of action when a compensating control needs to be applied? A. Record the risk as accepted in the risk register. B. Obtain the risk owner's approval. C. Inform senior management. D. Update the risk response plan. Â Suggested Answer: B This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.