A controller proposed a budget reduction for projects because the majority of implemented solutions resulted in little returns on investment (ROI) or operational improvements. The project manager objected and presented project assets showing all solutions having been demonstrated, accepted, and delivered within the relevant framework constraints. The project manager suggested that the issues may stem from the project evaluation and selection processes. What was the project manager demonstrating? A. Multiple stages of development that members may go through toward working formations B. Cause-and-effect identification in root cause analysis toward achieving project value C. Strategic negotiation techniques in determining budget priorities in future sessions D. Risk management in addressing impediments, obstacles, and blockers to project success B Correct Answer: B This question is in PMP exam For getting PMP Certificate