A customer asks the project manager about opportunities to create business value. What should the project manager do first in order to provide the customer with an appropriate response? A. Meet with the sponsor to review the business case. B. Examine the business value throughout the project. C. Meet with the product owner to review the backlog. D. Ask the team to organize a spike to identify more value. Correct Answer: B This question is in PMP exam For getting PMP Certificate