A customer has provided excellent feedback on the project. However, a key project resource is leaving the company. Which measure should mitigate the impact of this key resource's departure? A. Establish a proactive knowledge-sharing plan B. Offer a new contract to the resource who is leaving C. Develop a contingency budget to replace the key resource D. Update the risk register and inform the customer Correct Answer: A This question is in PMP exam For getting PMP Certificate