A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

QuestionsCategory: PMPA customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?
Admin Staff asked 1 year ago
A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product.
Which approach should the project manager take?

A. Ask the team to raise blockers or impediments in daily meetings.

B. Prioritize the tasks with high risks to reduce the number of iterations required.

C. Ask the team to challenge the project estimations for a faster delivery.

D. Prioritize deliverables based on business value and define frequent releases.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.