A customer support team has planned short, iterative cycles for working on customer-reported issues. Recently, there was a surge of high-priority issues that disrupted the original plan, and the team's manager is nding it difficult to manage the progress. Which approach should the project manager suggest using? A. Agile Scrum approach B. Agile Kanban approach C. Spiral approach D. Rapid application development approach Correct Answer: B This question is in PMP exam For getting PMP Certificate