A data center has recently been migrated to a jurisdiction where heavy fines will be imposed should leakage of customer personal data occur. Assuming no other changes to the operating environment, which factor should be updated to reflect this situation as an input to scenario development for this particular risk event?

QuestionsCategory: CRISCA data center has recently been migrated to a jurisdiction where heavy fines will be imposed should leakage of customer personal data occur. Assuming no other changes to the operating environment, which factor should be updated to reflect this situation as an input to scenario development for this particular risk event?
Admin Staff asked 6 months ago
A data center has recently been migrated to a jurisdiction where heavy fines will be imposed should leakage of customer personal data occur. Assuming no other changes to the operating environment, which factor should be updated to reflect this situation as an input to scenario development for this particular risk event?

A. Risk impact

B. Risk appetite

C. Risk likelihood

D. Risk capacity








 

Suggested Answer: A



This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.